INDEPENDENT NEWS

South Island generators must pay for HVDC upgrade

Published: Fri 7 Oct 2005 01:54 PM
Media statement Friday, October 7th, 2005
South Island generators must pay for HVDC upgrade
The full $520 million cost of Transpower’s proposed upgrade of the High Voltage Direct Current Link must be paid by the power generators benefiting from it, the Employers & Manufacturers Association (Northern) says.
“The cost of the upgrade should be met by South Island generator companies, not North Island consumers” said Bruce Goldsworthy, EMA’s Manager of Advocacy.
“If the cost is spread across power transmission nationwide, the South Island generators in effect would become subsidized and able to reap super profits.
“The reasons for allocating all the HVDC link costs to South Island generators are:
- The HVDC Link exists to allow South Island generators to access the North Island market. If they could not do this their revenue stream would be unsustainable.
- Market mechanisms need to ensure costs lie where they fall in all cases.
- If the cost of environmental effects are included, such as the carbon tax proposed for thermal generation, then the same should apply to renewable generation when additional costs are incurred in the transmission system.”
ENDS

Next in Business, Science, and Tech

TRENZ Bids Goodbye To The Capital, And Hello To Rotorua
By: Tourism Industry Aotearoa
Property Manager Launches New Training Standard As Govt Abandons Regulation
By: Impression Real Estate
What Makes People Tick Environmentally?
By: University of Canterbury
Release Of Gallagher Security’s Command Centre V9.10 Unlocks New Era Of Security Tech
By: Gallagher Security Management Systems
NASA Hand-picks Kiwi Nut Butter Brand Fix & Fogg To Travel To Space In NZ First
By: Fix and Fogg
Sailors To Revolutionise Our Understanding Of Pacific Biodiversity
By: Citizens of the Sea
View as: DESKTOP | MOBILE © Scoop Media