Full Steam Ahead !
Manatua Cable Leaves Factory on Freighter Bound for the South Pacific
Cable manufacture and testing complete
Freighter Thorco Liva contracted for 15,000km delivery
Environmental Approval Secured
4 OCTOBER 2019
Portsmouth New Jersey, USA
Avaroa Cable Ltd today confirmed that manufacture of the 3600km Manatua Cable is now complete.
The advanced fibre optic cable, its six branches for landings across Polynesia, and the 32 ‘repeaters’ have completed
the rigorous factory manufacture and quality processes, and factory acceptance tests in a specialist facility in
Portsmouth, New Hampshire, USA. Manufacture has taken many months to complete. The cable will provide up to 10Tbps
(10,000,000Mbps).
The Hong Kong registered 13,000 tonne freighter Thorco Liva has been contracted for the delivery to Samoa in preparation for the start of cable laying later this year. The 131m
vessel departed Portsmouth on 20 September heading for the Panama Canal in order to reach Pacific waters. The 15,000 km
journey will take several weeks to complete.
Loading of the cable onto the freighter has taken over two weeks, with end-to-end testing carried out at regular
intervals. This is to ensure that no damage has occurred to the cable during the loading process. The cable is
engineered for faultless operation over the cable’s 25 year life.
The news coincides with approval for the Manatua Cable’s Environmental Impact Assessment (EIA) study by the Government
of the Cook Island’s National Environment Service (NES). NES carefully assessed the activities associated with
installing and operating the cable, as well as the feedback from pubic consultations held earlier this year. Approval by
NES is a pre-requisite for the cable to move ahead.
Completion of the Trans Polynesian Information Superhighway is on target to be ready for service in May 2020.
Dr Ranulf Scarbrough, ACL CEO and Vice Chair of the Manatua Cable Consortium said: “This is a key milestone for the Manatua cable project and for a new era of communications connectivity for the Cook
Islands. Completion of the cable and an environmental green-light reflect a lot of hard work by some very dedicated
people and takes us another step closer to our goal – faster, cheaper, more reliable and more resilient connectivity.”
Nga Puna, National Environment Service Director said: “NES recognises that the Manatua Cable is a crucial project for the Cooks Islands but that doesn’t mean there can be
any compromise on our stringent environmental protection standards. NES carefully studied ACL’s proposals and used
independent expert advice to be certain those protections would be in place. I am delighted that NES has been able to
approve this project.”
Petero Okotai, Chief Executive, Cook Islands Investment Corporation said: “The Manatua Cable will provide a step-change in communications infrastructure of the Cook Islands, enabling and
underpinning efforts for the Cook Islands to access to a new world of new social and economic opportunities. It is great
to see the progress ACL is making in delivering this important investment.”