Processes to be strengthened
Processes to be strengthened
The Provincial Development Unit (PDU) administering the Provincial Growth Fund (PGF) is strengthening its systems and processes for assessing and approving requests for funding following an internal review, Provincial Development Unit head Nigel Bickle said today.
“The Provincial Development Unit accepts the findings of an internal review that due diligence on personnel associated with the Waste to Energy project should have been undertaken prior to approval of PGF funding for the project and a ministerial announcement,” Mr Bickle says.
The Waste to Energy project was approved for funding but that funding was put on hold as soon as issues arose. The internal review report released by the PDU today outlines the background to the issues and the process followed up until the Minister’s announcement.
“We also accept the recommendations made in the review. We fell below prudent standards of due diligence and we have apologised to the Minister for not getting this right,” Mr Bickle says.
“The public quite rightly expects government agencies to run a robust process before awarding contracts or approving funding. In this case we made a mistake by not completing appropriate checks on personnel associated with the Waste to Energy project.
“We agree there would have been enough time to complete these checks prior to any funding being approved and the subsequent ministerial announcement. The fact that these issues would most likely have been picked up in the contract negotiations process, post announcement and before any PGF funding was actually handed over, is no excuse.
“While this is not a defence, the team was in an
establishment phase and we were quickly transitioning from
an organisation set up to approve and manage around $11M/pa
in development funding to one responsible for administering
$1Bn/pa. All projects that have had funding announced to
date will continue to undergo due diligence processes in
accordance with the standards that have been put in
place.”
The following changes to our processes and
systems have been made:
• Due diligence on personnel is
now carried out before applications are considered by
Ministers and other decisions makers for funding and
announcements.
• If due diligence cannot be completed
within the available time, then the Minister’s Office will
be informed of this risk, and where practicable, an
announcement delayed until the process has been
completed.
• The introduction of a robust application
process that is proportional to the types of
applications.
• Applicants will also need to declare
that they have not been convicted or are under investigation
for any offences bearing on the operation of the
business.
• We are also asking the Office of the
Auditor General to provide feedback and suggestions on any
further improvements we could make.
The report is at http://www.mbie.govt.nz/info-services/sectors-industries/regions-cities/regional-economic-development/documents
[ends]