Scoop has an Ethical Paywall
Licence needed for work use Learn More

Gordon Campbell | Parliament TV | Parliament Today | News Video | Crime | Employers | Housing | Immigration | Legal | Local Govt. | Maori | Welfare | Unions | Youth | Search

 

Consumers object to paying for Transpower’s cost overrun

Consumers object to paying for Transpower’s cost overrun

The original approved cost for Transpower’s North Island Grid Upgrade (NIGUP) was set by the Electricity Commission at $824 million; however costs overran this by $70 million. Now the Commerce Commission has released a draft decision approving $52 million of the over spend.

“This means it is the consumer who will be picking up the tab,” says Ralph Matthes, Executive Director of the Major Electricity Users’ Group.

“We don’t mind paying for things we actually use, and get value from, but no one wants to pay for things that add no value.”

NIGUP is the first and only 400kV direct current (DC) voltage line in NZ. It was designed to operate for a few years at 220kV and then as Auckland demand increased it would be re-rated up to 400kV.

“Transpower went ahead with this extremely expensive upgrade even though, as MEUG pointed out, we expected demand in Auckland would fall or grow modestly. This is what has happened and it is unlikely NIGUP will ever be used to its full capacity.

In a competitive market the entity that overinvested is the one which bears the costs and so should Transpower, not electricity consumers.”

The Electricity Authority estimated the original approved budget for NIGUP of $824 million costs consumers $112 million per year but only produces $16 million per annum of benefits. MEUG estimate the $52 million cost overrun will add another $5 million to annual charges.

“Consumers are now expected to pay a further $5m per year on top of the $101 million for services they derive no benefit from. This is galling for all consumers and particularly for South Island consumers that benefit little if anything from NIGUP but must pay whereas North Island generators shipping electricity into Auckland that have benefited from NIGUP pay nothing.

This draft decision might be correct according to the rules but that merely demonstrates that the rules are tilted in Transpower’s favour.”

The Commerce Commission is seeking submissions on 21st May ahead of a final decision.

ends


Advertisement - scroll to continue reading

© Scoop Media

Advertisement - scroll to continue reading
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 
 
 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

Featured News Channels