Near miss incident sends sharp reminder
Media release -
Near miss incident sends sharp reminder
WorkSafe says a near miss incident involving earth movers and electrical wires is a reminder to businesses to confirm that lines are not electrically live before beginning work, and to never make the assumption that they are not live.
The message comes after Dimac Contractors Limited was sentenced today following an appearance 10 days ago in the Hutt Valley District Court.
Dimac faced one charge after a near miss incident in April last year. Workers were clearing top soil from a development site in Upper Hutt when a digger struck a 240kv power line. The impact caused a power pole to snap and fall to the ground. The power line became entangled on the digger and was later cut off by a different worker.
Dimac had been told by the property developer that they thought the lines were dead, but they were not sure, so to treat them as live.
The power lines, assumed by the contractor to be off, were in fact live and risked the lives of two workers involved in the incident.
WorkSafe’s Chief Inspector Investigations Keith Stewart said both workers were lucky to escape the incident unscathed.
“The hazards associated with electricity are well known and with four power poles in clear view on the site, the hazard should have been noted and testing completed to assess the state of the power lines.
“The fact that neither worker was hurt is not relevant in this instance. The risk posed was great and the contractor was negligent in ensuring the health and safety of their workers. Those working with and near to power lines should assume they are alive, until they have been informed otherwise”.
Notes:
- The fine
imposed by the judge was $90,000.
- Dimac
Contractors Limited was sentenced for one charge under
sections 36(1)(a), 48(1) and (2)(c) of the Health and Safety
at Work Act 2015
1. Failed to ensure, so far as was
reasonably practicable, the health and safety of workers who
worked for the PCBU, while the workers were at work in the
business or undertaking, namely carrying out earthworks, and
that failure exposed the workers to a risk of death or
serious injury, arising from exposure to live
electricity.
- The maximum penalty was a fine not
exceeding $1,500,000.
WorkSafe’s investigation found that Dimac failed to:
• develop an adequate
process to identify and manage electrical hazards;
•
ensure the power lines were not live before work
commenced;
• ensure work was done in accordance
with the safe distances in the New Zealand Electrical Code
of Practice for Electrical Safe Distances;
•
instruct workers not to approach the power line after the
pole had fallen;
• restrict access by workers to
the fallen line;
• wait for professional advice
as to the status of the fallen power line before allowing
work to
continue.
ENDS