Pipeline Repair: Status Update

Published: Fri 22 Sep 2017 11:41 AM
Pipeline repair: status update
The repair team has made good progress overnight. The replacement section has been welded into place and the initial weld inspections have passed. This is an important milestone. The second weld inspection will be carried out tonight.
We remain on track to deliver in the early part of the repair ‘window’, between mid-day Sunday the 24th and mid-day Tuesday the 26th. Settling, recertification and transport to the airport for use will take another 30 hours.
An inspection of the pipeline insulation along the two kilometre length of the kauri swamp, has confirmed the integrity of the pipeline insulation.
Alternative supply
The jet fuel truck-loading facility trial was completed successfully yesterday evening and jet fuel ‘bridging’ has now commenced in earnest.
ENDS

Next in Business, Science, and Tech

Global Screen Industry Unites For Streaming Platform Regulation And Intellectual Property Protections
By: SPADA
General Practices Begin Issuing Clause 14 Notices In Relation To The NZNO Primary Practice Pay Equity Claim
By: Genpro
View as: DESKTOP | MOBILE © Scoop Media