Ngatamariki Station boosts Mighty River Power’s Production

Published: Mon 2 Sep 2013 09:45 AM
News Release
2 September 2013
New Ngatamariki Station boosts Mighty River Power’s geothermal production, driving earnings growth
Mighty River Power today marked the completion and handover of its new 82MW Ngatamariki power station – expanding the Company’s geothermal production to more than 40% of its total generation and contributing to strong earnings growth.
Mighty River Power’s Chief Executive, Doug Heffernan, said the plant near Taupo was completed within the $475 million forecast detailed in the Company’s prospectus and had proven performance above design specifications in testing over the past three months.
“We’re delighted with a project of this scale – the largest of its type in the world – to see it successfully completed, and with power output now expected to be 3MW (4%) higher than spec, which will be positive for the plant’s economics and cash flow into the future. We also expect the project to come in slightly under the total cost forecast.”
Dr Heffernan said the new station would add close to 700GWh of annual electricity production, equivalent to the electricity use of about 80,000 households. With the completion of the new Ngatamariki station, he said the Company now had about 2,800GWh or 40% of its production coming from low operating cost renewable geothermal which “gives us additional strength and resilience in our core business”.
“This reliability of geothermal, as a major component of our portfolio, is a distinctive competitive strength for us in the New Zealand electricity market.”
“The completion of this project is an important strategic milestone for Mighty River Power, and the key driver of the 27% growth in Operating Earnings we’re forecasting this financial year (FY2014) above FY2013 results announced last week.”
Mighty River Power’s GM Development, Mark Trigg, said the plant reached full capacity for the first time at the end of June and had now successfully completed a continuous 30-day reliability run, enabling formal handover from the principal contractor Ormat Technologies Inc.
The plant had produced more than 150GWh during commissioning, contributing to cash flow. With the official handover, Ngatamariki has joined Mighty River Power’s operating portfolio and the generation revenue is now recognised as income by Mighty River Power, rather than an offset to project cost.
Mr Trigg said: “This project has been more than a decade in the planning since the geothermal development rights over the land were secured with our partners in 2000. Today, as our third major geothermal project completed since 2008, this extends our successful track record in geothermal development in New Zealand.
“Particularly pleasing was the significant reduction in the Total Recordable Injury Frequency Rate (TRIFR) compared with the previous project (Nga Awa Purua) and vindicates the focus that we have been applying across the Company to improving Health and Safety outcomes.
“The completion of Ngatamariki also means the significant capital expenditure – of more than $1.4 billion – that the Company has invested in geothermal assets in New Zealand over recent years is at an end, with Mighty River Power unlikely to build a new large power station here in the next three to five years due to the current weak electricity demand outlook,” Mr Trigg said.
ENDS

Next in Business, Science, and Tech

Gaffer Tape And Glue Delivering New Zealand’s Mission Critical Services
By: John Mazenier
Ivan Skinner Award Winner Inspired By Real-life Earthquake Experience
By: Earthquake Commission
Consultation Opens On A Digital Currency For New Zealand
By: Reserve Bank
Ship Anchors May Cause Extensive And Long-lasting Damage To The Seafloor, According To New NIWA Research
By: NIWA
A Step Forward For Simpler Trade Between New Zealand And Singapore
By: New Zealand Customs Service
68% Say Make Banks Offer Fraud Protection
By: Horizon Research Limited
View as: DESKTOP | MOBILE © Scoop Media