Christmas Work on Rail Networks
MEDIA STATEMENT
For
immediate release
13th December,
2011
Christmas Work on Rail Networks in
Wellington and Auckland
While the rest of the country is on holiday
hundreds of railway staff and contractors are working around
the clock on busy work programmes in Wellington and Auckland
preparing the rail networks for improved commuter services
and electric trains.
“Staff will be working round the clock to complete work that will improve our infrastructure and increase the reliability of our operations,” says KiwiRail Network General Manager Infrastructure and Engineering, Rick Van Barneveld.
“We intend to take full advantage of the line closure and have a number of major works planned that couldn’t be done with the trains running. During the network closure, passenger services will be replaced by buses and freight will be maintained using short road bridging.
More information about the Christmas timetables is available at www.tranzmetro.co.nz for Wellington and www.maxx.co.nz for Auckland."
The focus of the works in the Wellington region will enable staff to work on upgrading Tunnel Two on the North Island Main Trunk (NIMT), replacing overhead wiring and poles south of Paekakariki, upgrades to the Naenae and Kenepuru stations and slope stabilisation work on the Johnsonville and NIMT lines. While the work is underway freight services will be routed through the Wairarapa while Tunnel Two is closed.
General maintenance activities on hard to get at infrastructure will also be completed during this time.
In Auckland KiwiRail is preparing for the electrification of the rail network at multiple sites around the network. Work starts in from next week in Parnell, and expands to the remaining network from Boxing Day onwards, for up to three weeks in some places. Auckland activities include:
• The replacement of
four rail overbridges (Orakei Rd, Mt Wellington Highway,
Mountain Rd and Morrin Rd) and five footbridges (Orakei,
Meadowbank, Ellerslie, Puhinui and Otahuhu)
•
Lowering the tracks in the Parnell gully to allow for a
proposed station at the site in the future (on behalf of
Auckland Transport)
• The commissioning of a
new signalling system between Morningside and Swanson
stations
• Major track works at Wiri, and
around Papakura station and structural works at Britomart in
advance of electric trains arriving
•
Continuing the installation of overhead wires and masts
along the Western, Southern and Onehunga Branch Lines;
ENDS