Waiuku Wind Farm Declined Fast-track Consent

Published: Tue 20 Aug 2024 02:40 PM
An independent panel has declined resource consent for a wind farm in Waiuku, Franklin.
LET Capital Number 3 Limited applied for resource consent under the COVID-19 Recovery (Fast-track Consenting) Act 2020.
The project would have involved constructing and operating a wind farm with 13 wind turbine generators to supply electricity to the national grid.
The decision comes 154 working days after the application was lodged with the Environmental Protection Authority.
The Environmental Protection Authority is not involved in the decision-making. We provide procedural advice and administrative support to the panel convenor, Judge Laurie Newhook, and the expert consenting panel he appoints.
Read the Waiuku Wind Farm decision report : https://www.epa.govt.nz/fast-track-consenting/referred-projects/waiuku-wind-farm/the-decision/
More about fast-track consenting : https://www.epa.govt.nz/fast-track-consenting

Next in New Zealand politics

Major National Conservation Milestone For Rare Native Frog Species
By: Zealandia
Next Steps On Electrifying New Zealand
By: New Zealand Government
Minister Must Listen To Court’s Uber Ruling And Abandon Contractor Reform
By: NZCTU
Local Iwi To Rally Against Sewerage Pipeline Through Sacred Site
By: Reanga Taketake
Fast-track Approvals Bill Still Fundamentally Flawed, Despite Welcome Changes
By: Forest And Bird
Open Letter To The Government: Peace And Security For Aotearoa New Zealand
By: New Zealand Quakers
View as: DESKTOP | MOBILE © Scoop Media