Gladstone Road Realignment Fast Tracked As Second Landslip Permanently Closes Road.

Gladstone Road, Levin, suffered a substantial landslip in February 2017. Since then the slip has continued to be active and as a result the residents have been subjected to multiple, regular, short term road closures.

The heavy rainfall event on Sunday 28 June has now brought down a second major landslip on Gladstone Road. Due to the severity of the second slip, Council has since decided to abandon this at-risk section of Gladstone Road and fast track the building of a new 1.4km alignment for Gladstone Road.

The new route will bypass the most at-risk sections of Gladstone Road. The project will build two new bridges across the Makahika Stream, one at each end of a 1.3km section of new road built on a terrace between the Makahika Stream and Ōhau River.

In the interim a new temporary road, with temporary crossing points across the river, will be constructed to by-pass the at-risk section. This will give residents a safer alternate route during the construction of the new permanent route.

It is timely that last week Council was successfully approved funding from Waka Kotahi to build the more resilient access route for the Gladstone Road community.

The total project cost is $4.8 million, of which 62% is subsidized by Waka Kotahi.

Roading Services Manager James Wallace said, “The road will be a welcome addition for the Gladstone Road community. He thanks the community for their patience and understanding through what has been a testing time for everyone.

Advertisement - scroll to continue reading

The second landslip has now caused permanent closure of Gladstone Road. This leaves one resident only access route, which requires a 4x4, which is not ideal. We’re currently constructing a second emergency access, but it’s fair to say, the sooner the permanent road is constructed the better. The new road will be much safer for residents and visitors to the area.”

With the section of Gladstone Road now permanently closed, contractors are building an emergency access road near where the final alignment of the new road will be. This access road will be safe to use for 2 wheel drive cars. It is anticipated that this will be completed and ready for use within the next two weeks.

Work is also underway to improve the safety of the Trig Road for users, and repair various issues past the slip sites, including scouring on the abutment of Wai-iti Stream No.2 Bridge.

Construction of the new Gladstone Road is expected to be completed over the next 12 months.

© Scoop Media

Advertisement - scroll to continue reading
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 
 
 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

Featured News Channels


 
 
 
 

Join Our Free Newsletter

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.