Visitors to the Far North at Easter will be able to take the direct route via State Highway 1 through the Mangamuka
Gorge.
The gorge route will be open to light vehicles from Easter Friday to Monday (2-5 April) between 8:00am and 7:00pm. Heavy
vehicles will have to keep using the SH10 detour route.
“Vehicles will travel in one-way convoys approximately every fifteen minutes over the 4.2km route. They will be escorted
by lead and tail vehicles to ensure everyone sticks together and gets through before the next convoy sets off,” says
Waka Kotahi Northland System Manager Jacqui Hori-Hoult.
“Convoys will run continuously through the day, without waiting for a set number of vehicles before setting off. It will
be a bit like a stop/go traffic operation, except that each line of vehicles will be escorted.”
“Motorists will have to approach the convoys with some flexibility as they won’t run to a strict timetable. It will
depend on how many vehicles turn up on the day. People might miss getting on the end of a convoy and have to wait up to
twenty minutes for the next one.”
Caption: the pile wall supporting the road is nearly finished and work is under way to build a retaining wall above the
road to restore it to two lanes
The road is still reduced to one lane past two slip work sites on the northern side of the gorge summit. It’s been
closed since a big storm last July, though it was open for three weeks over Christmas.
“Waka Kotahi wants to open the gorge over the Easter holiday weekend because of the benefits visitors will bring to the
local economy. But also, for the local community, it provides a break from the extra time and cost of having to use SH10
detour route, which adds 20-30 minutes to the journey.”
“If the Easter convoys work well and there’s a demand, we’ll look to open the road to convoys on most weekends after
Easter.”
“There will be some weekends where the repair work is at a stage where it won’t be possible for safety reasons to allow
the public through the work area. We’ll give 24 hours notice of those weekend closures.”
Jacqui Hori-Hoult says work to restore the road to two lanes by the middle of the year is going to plan. The total
estimated cost of the Mangamuka Gorge repairs is 13.8M. This includes the ongoing slip repairs and the cost of the
initial emergency response to last July’s storm damage which closed the road.
For more on the Mangamuka Gorge repairs see https://www.nzta.govt.nz/projects/sh1-mangamuka-gorge-slip-repairs/Plan ahead for a safe, enjoyable journey. Keep up to date with:COVID-19 services update: nzta.govt.nz/COVID19Traffic updates: journeys.nzta.govt.nz/trafficFacebook Auckland: facebook.com/nztaaklFacebook Northland: facebook.com/nztanorthlandTwitter: twitter.com/WakaKotahiAkNthJourney planner: journeys.nzta.govt.nzPhone: 0800 4 HIGHWAYS (0800 44 44 49)