Auckland Airport has brought forward budgeted and planned runway pavement replacement work with construction beginning
on the $26 million project in two weeks.
The outbreak of COVID-19 and the reduction in flights, particularly large long-haul aircraft, presented an opportunity
to have another look at the proposed construction windows, said André Lovatt, General Manager of Airport Development and
Delivery.
“We’ve experienced a significant reduction in flights and passenger numbers, with aircraft movements currently 90–95%
lower than a normal busy day. This project has been planned for some time, but it was clear that we had an opportunity
to bring construction forward to the earliest available time while runway movements are at an all-time low.
“Safety continues to be our number one priority, and I’d like to thank our aviation partners for working alongside us in
order to create a robust plan for undertaking this work. As an industry we’re facing enormous pressure and we have
appreciated how these stakeholders have prioritised the collaboration needed to produce a safe and workable solution
earlier than originally planned,” said Mr Lovatt.
Delivered by Brian Perry Civil, the project will create work for 150 people over the next three months and involve the
removal and replacement of 280, 36m2 slabs in the eastern end of the touch down zone. The project will see 12,000 tonnes
of concrete laid 500mm thick to create the heavy industrial-grade pavement necessary to withstand landings of some of
the heaviest and largest aircraft in the world, taking off at weights of up to 500 tonnes.
Aircraft will still continue to use the existing runway, which will be shortened by 1.1km during the 8 to 10-week
construction period. This method, called a displaced threshold, is a common practice at airports worldwide and allows
work to be carried out safely while aircraft continue to operate. Using an existing taxiway (contingent runway option)
was also considered but the added complexity of converting the taxiway to a safe, operational runway in a short time
frame meant it was not possible.
Mr Lovatt said in normal circumstances, a displaced threshold method could result in the need for airlines to reduce
aircraft weight, but with fewer fully laden aircraft flying it was not anticipated.
“Carrying out slab replacement work is a normal part of maintaining safe airfield operations and one undertaken
regularly by airports around the world. Our runway, which was originally constructed in 1965, has been developed and
renewed over the years as part of a programme of work that follows recognised standards and is overseen by independent
experts.”
The runway pavement replacement is a critical component of Auckland Airport’s much reduced infrastructure development
programme over the next couple of years, one which prioritises selected capital projects that are focused on essential
safety and asset maintenance.
Auckland Airport has deferred the vast majority of its infrastructure development programme – a series of projects that
had been designed to cater for growth in passenger numbers, projected to double by 2044.
“It’s extremely disappointing to put on hold much of the $1.2 billion worth of construction projects already underway
around the precinct prior to the COVID-19 outbreak. But with no certainty around when the aviation market will recover
it just isn’t realistic to keep progressing these projects at this point in time.”
The safety case for the runway works has been reviewed and approved by the Civil Aviation Authority.
Aviation partners for the project were: Airways, Airwork, Air New Zealand, Federation of Air New Zealand Pilots (FANZP),
New Zealand Air Line Pilots’ Association (NZALPA), Qantas Group and Tasman Cargo Airlines.