Planning is underway for a permanent solution to beachfront erosion at Pare St, caused by spring tides last week.
Emergency works were carried out over the weekend to secure three beachfront properties and stop a septic tank from falling into the ocean, with the installation of rock along the dune.
Staff reassessed the properties, the protection works and remaining gabion baskets and determined the emergency works had secured the area and stopped further erosion.
We’re continuing to monitor the affected properties and keep homeowners informed.
The emergency works were completed under Section 330 of the Resource Management Act. An application for retrospective consent for the work will be lodged within 20 working days.
Any erosion protection work must comply with the New Zealand Coastal Policy Statement, the RMA, the Wainui Beach Management Strategy and the Tairawhiti Resource Management Plan.
Residents have been informed that while rock was used as a temporary means of securing the houses and septic tank, there is a possibility it will need to come out again if retrospective consent isn’t granted.
“We’re working with our policy, regulatory and engineering staff, as well as the Wainui Beach community to find the right solution,” says director of lifelines, David Wilson.
“To be clear, a managed retreat of the houses and septic system is still an option but there will be further conversations at Council before any steps are taken on a permanent fix.”
Several other properties on Pare St had gabion baskets in front of the houses destroyed but there is no immediate risk to property, people or the environment.
We are seeking advice on whether the gabion baskets can be repaired or replaced.
“We have made the call to not undertake further works unless absolutely necessary as we believe any further works at this stage would not meet the test for emergency works under the RMA. Should things change down there we will reassess our options,” Mr Wilson said.
Excess rock from the emergency work is stockpiled at the end of Pare St in case any further damage occurs.
A full update, including a timeline of events and proposed next steps will be provided to Council at a later date.
ends

Next in New Zealand politics

On The Ethics (and Some Of The Economics) Of Lifting The Lockdown
By: Gordon Campbell
On Going To Level Four (and Scrapping The Olympics) Right Now
By: Gordon Campbell
Cabinet Approves Business Continuity Package In Response To COVID-19
By: New Zealand Government
Statement From Police Commissioner Mike Bush Following Guilty Pleas In Operation Deans Prosecution
By: New Zealand Police
Record transport investment in Draft GPS 2021
By: New Zealand Government
On The Loss Of Abortion Safe Zones
By: Gordon Campbell
On The Oil Price Smackdown, And On National’s Fatuous Crusade Against Red Tape
By: Gordon Campbell
Predator Free 2050 Strategy - Expert Reaction
By: Science Media Centre
On Buying Ventilators, And Expanding The Testing For Covid-19
By: Gordon Campbell
Advance payments to support contractors
By: New Zealand Government
Auckland Council Welcomes Package To Stimulate Economic Recovery
By: Auckland Council
Infrastructure Sector Sees 30 Percent Less Jobs
By: Infrastructure NZ
COVID-19 And The Fundamentals Of Living On A Timed Borrow
By: Nikko AM
Fixing Wellington’s Infrastructure Deficit Should Be Top Of Government’s To-do List
By: Business Central
Nation Steps Up To COVID-19 Alert Level 2
By: New Zealand Government
View as: DESKTOP | MOBILEWe're in BETA! Send Feedback © Scoop Media