Vandals land community with possible $60,000 bill

Vandals land community with possible $60,000 bill, cut in mobility access to Caroline bay

Vandals have landed the community with bill of up to $60,000 and have taken an important link to Caroline Bay out of service for up to six months.

The vandals broke into the Piazza lift plant room and caused severe damage to electrical circuit board panel and the hydraulic electrical system. The door mechanism at the base of the lift were also severely damaged.

There was also a large amount of diesel dumped into the Piazza fountain, risking major environmental damage and incurring a significant clean-up bill.

Mayor Damon Odey said that the council is working with police to identify the culprits, and would welcome any leads that the community could provide.

“This kind of intentional, abhorrent behavior is absolutely unacceptable. At the end of the day it is taking something from everyone in the community and landing them with a large bill in the process.

“The lift is an important way for people with mobility issues and people with small children in prams to access Caroline Bay from the City Centre and it’s particularly galling that some people think it’s okay to take this away for a bit of fun.

“If this wasn’t enough, pouring diesel into the fountain shows a complete disregard for the special environment of the Bay. If any diesel had escaped the fountain it would have gone straight into the stormwater system and from there into the bay.

“We’ll be working with the police to find out who was behind this, and we’d call on the community to share any information they may have.”

Advertisement - scroll to continue reading

An initial inspection of the lift by the manufacturing company has shown that if they can’t obtain the parts for the electrical circuit board due to its age and software running on it, that they will have to obtain these parts from Europe.

This could take up to 22 weeks to obtain the parts then 3 weeks to assemble and install and test the circuit board and software. If the circuit board has to be replaced then we are looking at a cost of up to $60,000.

“Caroline Bay is the heart of the city, and it’s heartbreaking that this has happened a time of year when everyone should be able to enjoy it, particularly with major events such as the Rock and Hop coming up,” said Damon.

“We’ll be doing everything we can to help the police find who did this, anyone with any information should contact the police in Timaru, or you can provide anonymous information to Crimestoppers at https://www.crimestoppers-nz.org/ or 0800 555 111.

“We need the community to put out a strong message that this is unacceptable.”


ends

© Scoop Media

Advertisement - scroll to continue reading
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 
 
 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

Featured News Channels


 
 
 
 

Join Our Free Newsletter

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.