Kaikōura SH1 - effect of Gita and timeline for repairs

Published: Wed 21 Feb 2018 02:50 PM
21 February 2018
Kaikōura SH1 - effect of Gita and timeline for repairs
The inland road (Route 70) into Kaikōura via Waiau and Mt Lyford was reopened this morning and it may be the sole route in and out of the town for some days, says the NZ Transport Agency.
The Kaikōura Coast was one of the places most significantly affected by Cyclone Gita with several large slips and rockfalls now blocking the road both north and south of the town.
“Work to clear these slips will take several days at least,” says Tim Crow, Earthquake Recovery Manager for the Transport Agency. “Multiple crews are working up and down the coast and on the Hundalees south of Oaro. A temporary, emergency access has been provided to residents of Oaro while the slips are being cleared.”
Rainfall was extreme in some places – more than 200 mm in 24 hours, and one site, Rosy Morn, south of Kaikōura, (site of previous slips), reported 302 mm of rain in 24 hours yesterday.
Maximum wind gusts yesterday evening were around 100 km/h on the coast.
“We will be doing our best to restore State Highway 1 as soon as possible and get the North Canterbury Transport Infrastructure Recovery team’s earthquake rebuild work back on track,” says Mr Crow.
“We encourage all people using the inland road to build in extra time and patience as there will be crews along that route also for some time.”
ends

Next in New Zealand politics

Die In for Palestine Marks ANZAC day
By: Peace Action Wellington
Penny Drops – But What About Seymour And Peters?
By: New Zealand Labour Party
PM Announces Changes To Portfolios
By: New Zealand Government
Just 1 In 6 Oppose ‘Three Strikes’ - Poll
By: Family First New Zealand
Budget Blunder Shows Nicola Willis Could Cut Recovery Funding
By: New Zealand Labour Party
Urgent Changes To System Through First RMA Amendment Bill
By: New Zealand Government
View as: DESKTOP | MOBILE © Scoop Media