QLDC Media Release: Mall Pipe Repairs Start Monday
Installation of new pipe in Queenstown Mall will begin on Monday 9 October 2017 following the burst main earlier this
week. QLDC contractors Veolia are preparing the site over the weekend, before undertaking the pipe installation which is
anticipated to be completed within the week. Veolia will also be installing a rider main to provide additional
resilience and security of future supply.
QLDC contractors Downer will undertake repairs to the pavement once the water main repairs are completed. This will
include re-levelling the underlying surface and re-laying the cobblestones. To enable safe, continued access to all
businesses in the lower Mall, Downer will stage the work due to the nature of the site. This phase is expected to take a
further two weeks.
With the exception of a brief late night or early morning shutdown whilst the new water main is activated, no disruption
to the water supply to properties is anticipated during the works. QLDC will advise business owners when details for the
shutdown are confirmed.
ENDS