Edgeware Road, St Albans, 3 months restrictions

• From Tuesday 26 April a section of Edgeware Rd, between Hills Rd and Geraldine St, is becoming one-way for about 3 months because of wastewater repairs at the intersection with Champion St.

• Traffic going east from Hills Rd will be detoured into Edward Ave and Barbadoes St.

Please support local businesses affected by the works.

Warrington Street, St Albans

• Warrington St, between Francis Ave and Barbadoes St, is one-way eastbound until Sunday 15 May. The detour for westbound traffic is Barbadoes St, Edward Ave, Forfar St and back onto Warrington.

• For 6 weeks SCIRT is repairing road and footpaths in Warrington St between Hills Rd and Woodville Street. Two-way traffic will be maintained but there will be lane shifts.

Barbadoes Street, St Albans

• Barbadoes St is one-way southbound between Canon St and Bealey Ave for about 2 more weeks. For northbound traffic the alternative route is Madras St, Canon St, and back to Barbadoes St.

North Parade, Richmond

• Work at night will be underway on North Parade, between Banks Ave and Randall St, to reconstruct the carriageway. This will take about 3 weeks.

• Traffic will be one-way northbound at night with detours for southbound traffic. Please lookout for changed traffic conditions. Please keep supporting local businesses in the Richmond area.

Advertisement - scroll to continue reading

Stanmore Road, Richmond

• Stanmore Rd will be down to one lane at the Gloucester St intersection for storm water repairs from Tuesday 26 April to Friday 29 April. Southbound traffic will detour via Armagh St and Fitzgerald Ave.

Ferry Road, Woolston, night work

• Wastewater repairs are being carried out for 4 nights from Tuesday 26 April near the corner of Ferry Rd and Alport Place. A stop/go traffic system will be in place near the worksite.

Woodham Road - Gloucester Street intersection

• The final stages of the work have progressed well and more quickly than expected. Traffic management will be removed around the middle of next week and the intersection fully opened.

Major wastewater repairs on Woodham Road, 7 months

Woodham Rd is closed at the intersection with Worcester St for about 7 months.

• Access to Woodham Rd, east of Worcester St, will be via Sewell St, Carnarvon St and Rowcliffe Crescent.

• Eastbound traffic on Woodham Rd will be diverted via Ngarimu St.

• A “no entry” sign is in place in Woodham Rd at Kerrs Rd and at Ngarimu St.

• The large wastewater main trunk, called the Southern Relief, is being repaired.

Worcester Street, Linwood

• The street remains one-way southbound between Dacre St and Linwood Ave.

Wainoni Road, one-way

• Traffic will be one-way between Breezes Rd and Portsmouth St until mid-May while final carriageway repairs are undertaken. Citybound commuters are detoured into Portsmouth St, Breezes and back on to Wainoni Rd.

New Brighton Road

• New Brighton Rd is closed between Palmers Rd and Baker St, for 2 months for major wastewater and storm water repairs and road resurfacing. The detour is Pratt St, Keyes Rd and Bowhill Rd.

Bassett Street, Burwood, detour

• Bassett St, between Travis Rd and Parnwell St, will be one-way northbound from Tuesday 26 April for around 2 weeks. The detour is Parnwell Street.

• Two-way traffic will be maintained in Bassett St, between Parnwell St and New Brighton Rd, using traffic lights. Please expect delays and allow for extra time in your journey.

Bower Avenue, Parklands

• For about 4 weeks Bower Ave is one-way southbound between New Brighton Rd and Palmers Rd for carriageway reconstruction.. The detour for northbound traffic is Palmers Rd.

• Bower Ave, between Beach Rd and Kristen Pl, has a progressive road closure until June 2016 for wastewater work.

• Bower Ave, between 516 Bower and Rue de la Mare, is one-way southbound for 1 more week. This will then progress to a section between Broadhaven Ave and 561 Bower Ave.

Beach Road, Parklands

The road closure on Beach Rd is now between Badger St and Pinewood Ave and will keep moving east towards the Beach Rd shops. The work is expected to take 4 more weeks.

Beach Rd, between Bower Ave and Effingham St, remains one-way eastbound for another week.

The section outside the shops- Naked Baker, Beach Road Fish Supply and North Beach Dairy - is two-way and parking is maintained. Please continue to support these local businesses.

If you would like to receive a fortnightly Parkland Traffic Update please email CIRinfo@fcc.co.nz

Queenspark Drive, Parklands

Queenspark Dr is one-way westbound between Bower Ave and Donnington St for 1 more week.Please continue to support the shops at the Parklands Mall while SCIRT works are underway.

Breezes Road, Aranui, progressive one-way for 5 months

Breezes Rd is one-way eastbound between Pages Rd and Cuthberts Rd. The detour is Cuthberts Rd, Nugent St, Shortland St, Pages Rd.

Aranui -Wainoni

• This area has several road closures. Please take care. SCIRT is installing a new more earthquake-resilient vacuum wastewater system. See the Aranui map for road closures, bus routes and detours.

Governors Bay Road, Rapaki, restrictions for 2 months

Retaining wall repairs outside 191 mean the westbound lane is closed around the work site. Two-way traffic is maintained with temporary traffic lights.

Shirley Road, short detour

• Traffic going east towards The Palms shopping centre is being detoured, because of culvert repairs. The detour is Emmett St, Orontes St and Quinns Rd back onto Shirley Rd.


© Scoop Media

Advertisement - scroll to continue reading
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 
 
 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

Featured News Channels


 
 
 
 

Join Our Free Newsletter

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.