SCIRT traffic update: Week starting Monday, 25 January 2016
SCIRT traffic update: Week starting Monday, 25 January 2016
Stronger Christchurch Infrastructure Rebuild Team (SCIRT) is ramping up its work for 2016 and at times that will impact on local businesses. Please go out of your way to support them
Woodham Rd -
Gloucester St intersection, restrictions for about 4
months
Please support your local businesses that
are currently affected by this work.
•
Wastewater repairs mean lane reductions and turning
restrictions at the Woodham Rd - Gloucester St
intersection.
• Temporary lights are in place
to help traffic flow.
Hills Rd, Shirley,
reduced lanes
• From Monday 25 January
SCIRT is working on Hills Rd between Warden St and Shirley
Rd for about 3 months repairing damaged storm water, roads,
footpaths and kerb and channels.
• Two-way
traffic will be maintained. Bus and cycle lanes will be
closed to make room for the worksite. Please take care
around merging cyclists.
• Hills Rd, between
Guild St and Dudley St, is one-way
northbound.
Strickland St,
Sydenham
Strickland St, between Milton St and
Boon St, will be one-way heading north for 2 days in the
week starting Monday 25
January.
Bower Ave, Burwood
• From Monday 25
January has a road closure between Queenspark Drive
and Rue de la Mare while wastewater renewal work is underway
near the intersection of Queenspark Dr and Bower Ave.
•
Temporary traffic lights will maintain access to and from
Queenspark Dr from the southern side of the Bower Ave
intersection.
• Queenspark Dr will be one-way
for westbound traffic only, between Donnington St and
Cottonwood St, for about 3 weeks from Monday 25
January.
Fendalton Rd
Please
watch for lane shifts while storm water repairs are carried
out between Deans Ave and Holmwood Rd.
Burlington St, Sydenham, is closed to traffic going south between Brougham St and Colombo St for wastewater repairs.
Beach Rd, New Brighton – progressive
road closure where major wastewater works are
underway
• A SCIRT crew continues
wastewater renewal work along Beach Rd from Ascot Ave to 144
Beach Rd for another 5 months. A progressive road closure
will be in place around the immediate work area.
•
A second crew continues on Beach Rd between Effingham St and
Bower Ave for about 2 more weeks. Currently a road closure
is in place between property numbers 149 and 101.
•
This week a temporary road closure is in place while sheet
piles are installed in preparation for the lift station
installation.
• A one-way system will be in
place from Monday 25 January, between Bower Ave and Pinewood
Ave, for traffic heading westbound only. This will be in
place for the duration of the installation work.
•
Parking outside the Beach Road businesses (the Naked Baker,
Beach Road Fish Supply and North Beach Dairy) will be
maintained. Please continue to support the local
businesses.
Beach Rd, storm water and
partial road rebuild
• Beach Rd
between Bower Ave and 117 Beach Rd is closed for storm
water, road, footpath and kerb and channel repairs. The work
is being carried out alongside waste water repair work in
the same section of Beach Rd.
• The road
renewal is expected to take about 3
months.
Ferry Rd, Woolston
Has
storm water repairs between Hopkins St and Dampier St.
Two-way traffic is maintained but there may be
delays.
Bealey Ave, between Madras St and Packe St, has reduced lanes for wastewater repairs for about 2 months. Please look out for cyclists.
Avonside Drive between Fitzgerald Ave and Stanmore Rd is one-way going west towards the city for road and kerb repairs. Traffic travelling east is being detoured into Stanmore Rd and Gloucester St.
Marine Parade
A progressive
one-way system is in place between Beach Rd and Pacific rd
for southbound traffic for about 2 months for road
renewal.
Moorhouse Ave overbridge is reduced to one lane each way for the duration of the repair project.
Worcester St, Linwood
•
Worcester St is closed between Woodham Rd
and Dacre St with limited access to residents only.
•
Worcester St remains one-way southbound between Wyon St and
Linwood Ave for major wastewater repairs.
New
Brighton Rd, Burwood
Between Bassett St and
Anzac Drive, is closed for installation of two wastewater
pressure mains which is a 5 month project.
Shirley
Rd – Short detour
Traffic going eastwards
towards The Palms shopping centre is being detoured, because
of wastewater repairs, through Emmett St, Orontes St and
Quinns Rd back onto Shirley
Rd.
Aranui/Wainoni
Please take extra
care around this busy area as SCIRT installs a new resilient
vacuum wastewater system for this community. See the Aranui map for road closures, bus routes
and detours.
Dudley Street, Shirley,
between Hills Rd and Slater St, has a road closure
from 12 January for about 2 months for renewal of the road
surface.
Please visit the Metro website www.metroinfo.org.nz or phone Metro Info on 366 8855 for any bus service changes.
Check the best way to get in and around the city at: www.tfc.govt.nz