Port Otago leads way to next generation
Port Otago leads way to next generation
Port Otago
will become the first port in New Zealand to deepen its
shipping channel for the next generation of container
shipping as part of a $30 million upgrade over the next two
years.
The infrastructural works programme, ‘Next Generation Port Otago’ will allow larger ships to access Port Chalmers while bolstering the port’s services to exporters.
Geoff Plunket, Port Otago Chief Executive, said Next Generation was a forward looking programme to upgrade the port’s efficiency and productivity for the next generation of its users. “It highlights our resolve to remain at the forefront of shipping and port activity in New Zealand and as a major contributor to the region’s economic growth.”
The capital works programme
includes:
1. Deepening of the shipping channel to
14 metres by end-2016
2. Deepening the berths and
sheet piling to support the wharf
3. Warehouse
expansion at both Port Chalmers and Sawyers Bay
4.
Actively investigating the purchase of a new tug and
barge.
The planned infrastructural expansion would add an
estimated 15 full time jobs to the port’s current
workforce of 300. It also follows on from a 10 year
programme of capital investment including the recent
purchase of a new 68-tonne bollard pull tug, a new pilot
launch, two new container cranes and a number of four-high
straddles.
Mr Plunket said continual infrastructure
upgrades were a necessary response to rapid changes to the
international shipping environment. “Our service is linked
to our capacity. It’s something every generation of the
Port has been aware of since our inception more than 130
years ago and it’s allowed us to stay in the vanguard of
shipping activity.
“To maintain our relevance within the international supply chain requires continued development, ensuring we can cater for larger container ships of the order of 6,000 to 8,000 TEUs and that there is enough cargo available to fill those bigger ships for decades to come.”
Port Otago is already the deepest container port in the country at 13 metres (chart datum or low tide) and is unique in that it can operate at all stages of the tide.
With resource consent to deepen the shipping channel to a maximum of 15 metres for larger ships Port Otago will become the first to begin actual dredging. The first milestone will be to deepen to 14 metres and this will be done in two stages, with deepening of the existing channel to 13.5 metres by end 2015 and to 14 metres by December 2016.
Mr Plunket said that while other ports may dredge their channel to a similar depth, they were limited in only being able to receive ships on slack water (the top or bottom of the tide) due to strong tidal flows experienced at these ports. “Unlike other ports we also own our own dredge, the New Era, which is able to complete the work on a cost efficient basis and with as little environmental impact as possible.”
In line with the channel deepening,
container berths would also be deepened, requiring
additional reinforcement of the wharf structures by
constructing sheet piles along the berth line as an
underwater retaining wall. “This is complex work and
following a two-stage tender process, Port Otago has
contracted Daniel Smith Industries to supply and drive the
piles. As the work can’t be undertaken while vessels are
at berth we will temporarily close the inner container wharf
to all vessels during the low volume season between 1 July
and mid-October this year.”
Following completion of the
berth sheet piling work, the 135 metre extension of
Container Wharf No 2 is expected to start in mid to late
2016.
Capacity at Port Otago will also be increased through expanding the Port Chalmers’ Back Beach warehouses, increasing on wharf dairy storage capacity by 25% and developing an additional 3,800m² warehouse at Sawyer’s Bay, which will add a further 10% to the port’s current warehousing capacity. Construction is expected to commence on both sites during the second half of 2015 and take about four months to complete at a total cost of about $11 million.
Aligned to the expansion, the port is
actively investigating the purchase of a new tug and
split-hopper barge at a cost of about $7 million. Said Mr
Plunket: “This will provide greater efficiency in
disposing of dredge material as it can be operated
separately from New Era activity. Further, it provides the
port with a flexible asset pool which could service all of
Port Otago’s maintenance dredging and marine structure
task for the next 20 years.”
- Ends
-