Lower Hatea River Crossing a $14.5 million boost
Media Release
Lower Hatea River Crossing a $14.5 million boost to local economy in 2012
The news around the Lower Hatea River Crossing is all good as 2012 draws to a close.
The $29 million project is 62% of the way to completion and $14.5million of contracts, more than half of total construction costs, have been let to local companies.
“We have just awarded the contract for 140 tonnes of steel ballast for the bascule (lifting section) to Donovan’s, a Whangarei engineering company,” said Whangarei District Council Infrastructure and Services Manager Simon Weston.
“Today we celebrate completion of the last pier for the bridge. That means remaining work on the bridge itself is focused around completing the bridge beams and deck, guard rails, hand rails and lighting, constructing an asphalt surface and concrete footpaths, installing the bascule itself and the hydraulic rams that will enable it to rise and close.
“While local companies continue with their work programmes, projects are also advancing well overseas. The bascule lifting section, being constructed in pieces in China, is nearing completion and will arrive here in two shipments in early February and early March. The hydraulic rams that will lift the bascule section are also nearing completion in Holland and will arrive here in late February.”
Mr Weston said the largest sections of the bascule would arrive by ship at Marsden Point and be transported by road to the site.
“This promises to
be a pretty big operation, the biggest single load being the
deck, 26m x 5m x 1m high, weighing 33 tonnes, followed
closely in size by the J4 arm (the lower half of the hook
structure). The comparatively smaller pieces will be
shipped to Auckland and transported by road.
Mr Weston
said the Port Road (bridge) roundabout is complete, and is
just awaiting line markings and signs which will be done in
conjunction with the Okara roundabout, which is open on one
side at the moment and due to be completed by the end of
January.
Preparation is progressing at the site of the Riverside Drive roundabout. The walls on either side of the large culvert that will run under the roundabout have been retained. The preload, designed to consolidate the soil under the roundabout and aid settling, is expected to be removed in February and work forming this roundabout will begin in March.
Coming up next year:
In January
The last bridge beams and
precast concrete deck sections will be installed, along with
bridge handrails and the concrete footpath on the Pohe
Island side of bridge. The Okara Drive roundabout will be
completed and work will continue on the Pohe Island road,
drainage works at the Riverside Drive roundabout, and
electrical installation.
February
The first bascule
section shipment will arrive and assembly will start on
site. The hydraulic rams will arrive and guardrails and
facia panels will be installed on the Port Road side of
bridge. The Pohe Island road will be completed and the
pre-load will be removed from the site of the Riverside
Drive roundabout. Construction for the control room for the
bascule will start.
March
The second bascule section
will arrive and assembly will be completed on site. Hand
rails will be installed and the concrete footpath on the
Port Road side of bridge will be poured. Construction will
begin on the Riverside Drive roundabout. Pontoons and fender
piles will be installed in the River, and the control room
will be completed.
April
The bascule section will be
launched out over the River. Work will continue on the
Riverside Drive roundabout construction and landscaping will
start.
May
The bascule section will be commissioned
and work will continue on the Riverside Drive roundabout.
June
The Riverside Drive roundabout will be
completed.
July
The project will be completed and an
opening ceremony will be held.