Wharf Repairs on Time and Below Budget

Published: Thu 11 Aug 2011 03:06 PM
11 August 2011
Wharf Repairs on Time and Below Budget
The Raglan Wharf is now as strong as it was when it was built in 1916. Repairs to the wharf structure were completed last week on time and below the original budget.
Waikato District Council water and facilities general manager Richard Bax says the work has exceeded the scope of the original contract, as the extent of the corrosion to the wharf structure was worse than anticipated.
“The contractor, HEB Structures have completed the work to a very high standard and performed well given the change in scope and some very challenging tidal conditions.
“The final cost for the wharf repairs is $635,096. This is significantly lower than the engineer’s estimate of $827,500 even though the volume of work increased by around 14m3,” he said.
Now the wharf repairs are completed the pressure to complete the wharf building is on. The architects are now completing the internal floor plan.
“Developing the final drawings for the internal plan of the building is a detailed process and it has taken some time. The architects will have the final drawings completed by the start of October,” said Mr Bax.
To fast track the process, Waikato District Council will send out a request for ‘Expressions of Interest’ to builders next week. This means the work can be costed by a number of builders as soon as the plans are completed.
ENDS

Next in New Zealand politics

New Zealand Supports UN Palestine Resolution
By: New Zealand Government
Greens Welcome Cross-party Approach To Climate Adaptation
By: Green Party
Climate Change – Mitigating The Risks And Costs
By: New Zealand Government
Protest March Against Fast-track Bill Announced For Auckland
By: Greenpeace
Wellington Mayor Responds To Housing Minister’s District Plan Decision
By: Wellington Office of the Mayor
Modernising Census – Stats NZ
By: Stats NZ
View as: DESKTOP | MOBILE © Scoop Media