Te Uku makes the most of Waikato’s wind
Te Uku makes the most of Waikato’s wind
Thursday 10 February 2011
The Waikato’s first wind farm goes ‘live’ today when Prime Minister John Key formally switches on the turbines at the Te Uku wind farm.
The wind farm, of 28 Siemens turbines, is a joint alliance between Meridian Energy and WEL Networks. It is the first generation development project of its type in New Zealand between an electricity generator and retailer and a lines company.
Meridian Chief Executive Tim Lusk says it’s a proud day for the company. “This is a celebration of the efforts of our business partners, tangata whenua and the community working closely together to showcase a world class wind farm to the country,” he says.
“This wind farm is going to be one of the most productive in the world. Wind patterns at Te Uku mean that we will get twice the energy out of the turbines compared to that of the average wind farms elsewhere in the world.”
The wind farm has been generating electricity since November last year when the first turbine went live ahead of schedule. So far 22 turbines have been installed and 17 are producing electricity. All 28 turbines are expected to be operating by early March, with a capacity of 64.4MWs, enough to power 30,000 average homes.
“Te Uku will make a significant contribution to securing electricity supply in the Waikato. It will play an important role in providing energy into the national grid when electricity demand in the Waikato is low. In turn this will increase the security of supply not only for the Waikato region but the whole country.”
WEL Networks secured resource consent to build the wind farm in 2008. In 2009 WEL Networks and Meridian Energy entered into an alliance whereby Meridian would build and operate the wind farm while WEL would build and operate the electricity distribution line connecting the wind farm to the local network.
WEL Chief Executive Julian Elder says “this is a great demonstration of our commitment to leadership in driving community, regional and national benefits. Our staff, partners, iwi and the community have worked well together to achieve the best possible outcome for a project of this nature.”
Tim Lusk says the project team had to overcome many challenges during construction of the wind farm, including dealing with the site’s very steep terrain, which in places reaches heights of over 400 metres above sea level.
“They built 26kms of roads to transport the turbines to their foundations and built and maintained over 180 ‘erosion and sediment controls’ during the project. All of their hard work was recognised when they won Environment Waikato’s inaugural ‘site of the year’ award last year. I want to acknowledge the competence and professionalism of all our contractors and partners who have helped ensure that we reached today’s milestone.”
Important facts about the Te Uku wind farm
Once all 28 Siemens turbines are generating at Te Uku, Meridian’s total wind capacity will be increased by 19 percent taking it to 353MWs. New Zealand’s total wind generation capacity will be 570MW.
Te Uku will increase Meridian’s total (wind and hydro) installed generation by two percent to a total of 2,806MW.
At maximum capacity, one turbine can generate up to 2.3MW of electricity, enough to power all the homes within the town of Raglan.
Te Uku has a capacity factor of 44 percent, which is twice the average capacity factor of about 23 percent for wind farms internationally.
Te Uku wind farm will supply electricity to the local WEL Network.
Over 50 percent of the people working on the construction of the wind farm are locals who worked alongside experts from Denmark and Australia.
In addition to the construction of 26km of roads, 70km of cables have been laid throughout the wind farm to connect all 28 turbines to the new on-site switching station. All electricity will flow out via two circuits on a new 33kV, 25km distribution line built by WEL Networks.
WEL Network’s new line build, completed in October 2010, was the largest construction project undertaken by a lines company last year. The transmission line build plays an important part in WEL’s Western Network Upgrade, which when completed will increase security of supply for the region.
The project has brought significant financial benefits to the region, with over $30 million being invested in the local economy through employment, accommodation for people coming from outside the area, and retail spending.
The first turbine went live on 13 November 2010.
40,000 native plants have been planted on site.
Technical data on Siemens wind turbines at Te
Uku wind farm:
IEC Class: IIB
Rotor
diameter: 101 metres
Blade Length: 49 metres
Swept
area: 8000 m2
Hub height: 80 metres
Power
regulation: pitch regulated
Blade weight: 10.9
tonnes
Rotor weight: 50.9 tonnes
Nacelle weight: 81
tonnes
80 m tower weight (IEC IIB): 168.6
tonnes
Cut-in wind speed: 4 metres/second
Nominal
power: 12-13 metres/second
Cut-out wind speed:
25 metres/second
• The blade is manufactured in a
single operation, using a patented manufacturing process
invented by Siemens, based on vacuum-assisted resin
injection project without adhesives.
• The blades have
no glue joints between spars and shells, no weak points, no
easy access for water or lightning.
• Siemens supply
160 foundation bolts at 1475mm in length with a diameter of
42mm.
• Siemens provide a template to ensure the tower
matches the foundation.
• The bottom tower diameter
is 4.2m.
• Each turbine foundation contains 1000
tonnes of concrete (400 cubic metres, or 80-100 truckloads)
and 45 tonnes of steel
ENDS