Procession of bridge beams for the new Interchange

Published: Fri 9 May 2008 02:58 PM
MEDIA RELEASE
TRANSIT NEW ZEALAND WELLINGTON REGIONAL OFFICE
9 May 2008
Procession of bridge beams for the new Dowse Interchange
Large bridge beams will be taken from Ngauranga Gorge to the Dowse Drive intersection on SH2 next week before being put into place to continue forming the new Dowse Interchange.
The ready-made bridge beams will be taken from Ngauranga Gorge to the project site on SH2 overnight on Monday and Tuesday, 12-13 May.
The first of 14 beams is due to leave Ngauranga at 7.00pm on Monday night and make its way along the state highway ready for placement as part of the Dowse to Petone Upgrade Project.
Each 24m long by 2.5m wide beam, weighing 32 tonnes, is so large that it will be carried on a special truck and trailer unit travelling with a long-load escort.
Transit Regional Manager Graham Taylor says that as soon as the beams arrive on site they will be lifted into place to form the north and south spans of the new Dowse Interchange over SH2.
“With the first span of the ‘east bridge’ already in place above the Melling railway line this means that road users will really be able to see how the final structure is shaping up,” says Mr Taylor.
Transit thanks the public for their patience while we improve their journeys.
ends

Next in New Zealand politics

Maori Authority Warns Government On Fast Track Legislation
By: National Maori Authority
Comprehensive Partnership The Goal For NZ And The Philippines
By: New Zealand Government
Canterbury Spotted Skink In Serious Trouble
By: Department of Conservation
Oranga Tamariki Cuts Commit Tamariki To State Abuse
By: Te Pati Maori
Inflation Data Shows Need For A Plan On Climate And Population
By: New Zealand Council of Trade Unions
Annual Inflation At 4.0 Percent
By: Statistics New Zealand
View as: DESKTOP | MOBILE © Scoop Media