BUSWAY TRAFFIC BULLETIN: SATURDAY 11 TO FRIDAY 17 AUGUST
Transit New Zealandadvises motorists of next week’s proposed closures for work on State Highway 1 for Northern Buswayconstruction (weather permitting).
ONEWA RD
Sunday 12 August
(contingency 13 and 14 August)
Onewa Rdnorthbound and
southbound on-ramps closed from 10pmuntil 5amthe following
morning for realignment works.
• Diversion via
Northcote Rd on-ramps
NORTHCOTE RD
Monday 13 &
Tuesday 14 August (contingency 15 August)
Northcote
Rdsouthbound on-ramp closed each night from 10pmuntil 5amthe
following morning for paving works.
• Diversion
via Esmonde Rd southbound on-ramp
TRISTRAM
AVE
Wednesday 15 & Thursday 16 August
Tristram
Avesouthbound on-ramp closed each night from 10pmuntil
5amthe following morning for ramp widening works.
•
Diversion via Northcote Rd southbound on-ramp
Thursday 16 August
Tristram Avesouthbound off-ramp
closed from 10pmuntil 5amthe following morning for signage
installation, line marking and barrier removal.
•
Diversion via Northcote Rd southbound off-ramp
The above include contingency dates and diversion routes, which are subject to change. Work planned for adjacent junctions will be reviewed daily to ensure that no two consecutive over bridges or interchanges are closed at the same time and the correct diversions are in place.
Road users are requested to use the signposted detours whilst the closures are in operation.
Transit New Zealandapologises for
any inconvenience caused.