Busway Traffic Bulletin: Sat 31 March to Fri 6 Apr
Auckland Regional Office
30 March 2007
Busway Traffic Bulletin: Saturday 31 March to Friday 6 April
Transit New Zealand advises motorists of next week’s proposed closures for work on State Highway 1 for Northern Busway construction (weather permitting).
ONEWA RD
Sunday 1
April
Southbound on-ramp from Onewa Rd to SH1 - CLOSED -
overnight from 10pm until 5am for barrier placement.
*
Motorists are advised to follow the diversion via
Northcote Rd on-ramp southbound
* If unforeseen
circumstances prevent work at the above time, the closure
will be on Monday 2 & Wednesday 4 April
Sunday 1 & Monday
2 April
Southbound off-ramp from SH1 to Onewa Rd -
CLOSED - overnight from 10pm until 5am the following morning
for barrier placement.
* Motorists are advised to exit
at Northcote Rd or follow the diversion via Shelly Beach Rd
off-ramp, Curran St on-ramp & Onewa Rd northbound off-ramp
Sunday 1 & Monday 2 April
All SH1 motorway lanes
northbound between Onewa Rd & Northcote Rd - CLOSED -
overnight from 11pm - 5am the following morning for lane
marking & gantry construction.
* Motorists are advised
to follow the diversion via Northcote Rd on-ramp
northbound
Sunday 1 & Monday 2 April
Northbound
on-ramp from Onewa Rd to SH1 – CLOSED – overnight from
10pm until 5am the following morning for lane marking and
gantry construction.
* Motorists are advised to follow
the diversion via Northcote Rd on-ramp northbound
ESMONDE
RD
Monday 2 April
Northbound off-ramp from SH1 to
Esmonde Rd – CLOSED - overnight from 9pm - 5am for
pavement works.
* Motorists are advised to follow the
diversion via the Onewa Rd or Northcote Rd off-ramp
northbound
* If unforeseen circumstances prevent work
at the above time, the closures will be on Tuesday 3 &
Wednesday 4 April
Monday 2 April
Akoranga Dr eastbound
link to Esmonde Rd – CLOSED - overnight from 9pm - 5am for
pavement works.
* Motorists are advised to follow the
diversion via Northcote Rd.
* If unforeseen
circumstances prevent work at the above time, the closures
will be on Tuesday 3 & Wednesday 4 April
Monday 2 April
Southbound on-ramp from Esmonde Rd to SH1 - CLOSED -
overnight from 9pm until 5am for gantry construction.
*
Motorists are advised to follow the diversion via
Northcote Rd on-ramp
* If unforeseen circumstances
prevent work at the above time, the closure will be on
Tuesday 3 April
Tuesday 3 & Wednesday 4 April
Esmonde
Rd westbound between Barrys Point Rd & Lake Rd - CLOSED -
overnight from 9pm until 5am the following morning for
gantry construction.
* Motorists are advised to follow
the diversion via Lake Rd
NORTHCOTE RD
Sunday 1 &
Monday 2 April
Northbound off-ramp from SH1 to Northcote
Rd - CLOSED - overnight from 9pm until 5am the following
morning for paving works.
* Motorists are advised to
follow the diversion via Onewa Rd off-ramp northbound
*
If unforeseen circumstances prevent work at the above
time, the closures will be on Tuesday 3 & Wednesday 4
April
Tuesday 3 April
Southbound on-ramp from
Northcote Rd to SH1 - CLOSED - overnight from 9pm until 5am
for gantry works.
* Motorists are advised to follow
the diversion via Esmonde Rd on-ramp southbound
* If
unforeseen circumstances prevent work at the above time, the
closure will be on Wednesday 4 April
Tuesday 3 April
All SH1 motorway lanes southbound between Northcote Rd &
Esmonde Rd - CLOSED – overnight from 10pm until 5am for
gantry works.
* Motorists are advised to follow the
diversion via Esmonde Rd on-ramp southbound
TRISTRAM
AVE
Sunday 1 April
Southbound on-ramp from Tristram
Ave to SH1 – CLOSED – overnight from 9pm until 5am for
barrier placement.
* Motorists are advised to follow
the diversion via Northcote Rd on-ramp southbound
* If
unforeseen circumstances prevent work at the above time, the
closures will be on Monday 2 & Tuesday 3 April
If any of the contingency dates are required then all work planned for adjacent junctions will be reviewed to ensure that no two consecutive over bridges or interchanges are closed at the same time.
Road users are requested to use the sign posted detours whilst the closures are in operation.
Transit New Zealand apologises for any inconvenience caused.
Transit New Zealand Northern Busway Senior Project Manager Mark Johnson (09) 486 0054.
Visit www.transit.govt.nz or www.busway.co.nz for more information on the project.
ENDS