Proposed Closures for work on the Central Motorway
Auckland Regional Office
10 January 2007
Transit New Zealand would like to advise motorists of proposed closures for work on the Central Motorway Junction upgrade over the next week.
CMJ Stage 2
Full motorway
closures:
Sunday 14 until Thursday 18 January – CLOSED
– overnight from 9.30pm until 5am the following
morning:
• Southern Motorway (SH1) between Cook
St off-ramp and Hobson St on-ramp southbound
Sunday 14 and
Monday 15 January – CLOSED – overnight from 10.30pm
until 5am the following morning:
• Southern
Motorway (SH1) between Symonds/Port/Wellesley off-ramp and
Wellington St on-ramp northbound
Tuesday 16 January –
CLOSED – overnight from 10pm until 5am the following
morning:
• Southern Motorway (SH1) between
Nelson St off-ramp and Wellington St on-ramp northbound
Ramp and link closures:
Sunday 14 until Tuesday 16
January – CLOSED – overnight from 9pm until 5am the
following morning:
• Northwestern Motorway to
Southern Motorway (SH16 to SH1) link southbound
•
Northwestern Motorway (SH16) to Port Link portbound
Sunday
14 and Monday 15 January – CLOSED – overnight from
10.30pm until 5am the following morning:
•
Southern Motorway to Northwestern Motorway westbound (SH1 to
SH16) link
• Southern Motorway (SH16) to Nelson
St off-ramp citybound
Monday 15 and Tuesday 16 January –
CLOSED – overnight from 12.30am until 5am the following
morning:
• Hobson St on-ramp to Southern
Motorway (SH1) southbound
Tuesday 16 until Thursday 18
January – CLOSED – overnight from 9pm until 5am the
following morning:
• Grafton on-ramp to Southern
Motorway (SH1) southbound
Tuesday 16 January –
CLOSED – overnight from 10.30pm until 5am on Wednesday
morning:
• Wellington St on-ramp to Northern
Motorway (SH1) northbound
Tuesday 16 January – CLOSED
– overnight from 8.30pm until 5am on Wednesday
morning:
• Newton Rd on-ramp to Northwestern
Motorway (SH16) westbound
Wednesday 17 and Thursday 18
January – CLOSED – overnight from 10.30pm until 5am the
following morning:
• Hobson St on-ramp to
Northwestern Motorway (SH16) westbound
•
Northern Motorway to Northwestern Motorway (SH1 to SH16
link) westbound
During these times motorists are requested to follow the signposted detours while the closures are in operation.
Transit New Zealand regrets any inconvenience caused.
In the event of inclement weather, the closures will be postponed to the next fine evening.
The CMJ
Project
Stage 1 of Transit’s Central Motorway Junction
upgrade project, completed in January 2005, covers the
section of motorway between the Upper Queen St over-bridge
and Gillies Ave on- and off-ramps.
Phone 0800 ToFreeflow (0800 863 733).
Stage 2 of Transit’s Central Motorway Junction upgrade project extends from Bond St on the Northwestern Motorway (SH16) to the interface with CMJ Stage 1 near Symonds St and from Cook St on the Southern Motorway (SH1) to Symonds St. The SH16 Newton Rd to Western Springs Auxiliary Lane westbound widening project is included in CMJ Stage 2 works.
The Public Information Centre at 13-19 Howe St, Freemans Bay is no longer open on a regular basis. Any member of the public who has concerns about or wishes to discuss aspects of the project may make an appointment by phoning 0800 CMJ CORE (0800 265 2673).
ENDS