Busway traffic bulletin: Saturday 1 July to Friday 7 July
Transit New Zealand advises motorists of proposed closures for work on State Highway 1 for the construction of the Northern Busway over the next week (weather permitting).
Sunday 2
July/Monday 3 July/ Tuesday 4 July/ Wednesday 5 July/
Thursday 6 July
Northcote Rd SH1 southbound on-ramp –
CLOSED – overnight from 9pm until 5am to allow for drainage
works:
- Motorists to use Tristram Ave or Esmonde Rd
southbound on-ramps as alternatives.
Sunday 2 July/ Monday
3 July/Tuesday 4 July
All SH1 southbound motorway lanes
from Constellation Drive to Tristram Ave – CLOSED –
overnight from 10pm until 5am to allow for road widening
works:
- Motorists are to access the motorway southbound
at Tristram Ave, Northcote Rd or Esmonde Rd on-ramps.
A diversion will be in place for
motorists to exit the motorway at Constellation Drive and
re-enter the motorway at the Tristram Ave southbound
on-ramp.
- As part of this closure the Constellation
Drive SH1 southbound on-ramp will be closed during these
times.
Sunday 2 July/Monday 3 July/Tuesday 4
July/Wednesday 5 July/Thursday 6 July Esmonde Rd eastbound
between Barry’s Point Rd and Burns Ave – CLOSED – overnight
from 9pm until 5am to allow for the demolition of old Shoal
Bay Bridge:
- As part of this closure the left turn into
Esmonde Rd from Barry’s Point Rd will be closed at the same
times.
- Motorists to follow sign-posted detour up
Barry’s Point Rd, along Anzac Rd and into Lake Rd to access
Takapuna and Devonport.
Transit New Zealand regrets any inconvenience caused.
Transit New Zealand Northern Busway Project Director Clive Fuhr (09) 486 0054
Visit www.busway.co.nz or www.transit.govt.nz for more information on the project.