CMJ traffic bulletin: Saturday 22 April until Thursday 27 April

Transit New Zealand would like to advise motorists of proposed closures for work on the Central Motorway Junction upgrade over the next week.

CMJ Stage 2
Full motorway closures:
Sunday 23, Wednesday 26 and Thursday 27 April – CLOSED – overnight from 9pm until 5.30am the following morning:
- Southern Motorway (SH1) southbound between Cook St off-ramp and Hobson St on-ramp

Ramp and link closures:
Sunday 23 April – CLOSED – from 11pm until 5.30am on Monday:
- Hobson St on-ramp to Northwestern Motorway (SH16) westbound

Wednesday 26 and Thursday 27 April – CLOSED – overnight from 9pm until 5.30am the following morning:
- Newton on-ramp to Northwestern Motorway (SH16) westbound

Sunday 23, Wednesday 26 and Thursday 27 April – CLOSED – overnight from 9pm until 5am the following morning:
- Northwestern Motorway (SH16) citybound to Newton Rd off-ramp

During these times motorists are requested to follow the signposted detours while the closures are in operation.

Transit New Zealand regrets any inconvenience caused.

In the event of inclement weather, the closures will be postponed to the next fine evening.

The CMJ Project
Stage 1 of Transit’s Central Motorway Junction upgrade project, completed in January 2005, covers the section of motorway between the Upper Queen St over-bridge and Gillies Ave on- and off-ramps.

Advertisement - scroll to continue reading

Phone 0800 ToFreeflow (0800 863 733).

Stage 2 of Transit’s Central Motorway Junction upgrade project extends from Bond St on the Northwestern Motorway (SH16) to the interface with CMJ Stage 1 near Symonds St and from Cook St on the Southern Motorway (SH1) to Symonds St. The SH16 Newton Rd to Western Springs Auxiliary Lane westbound widening project is included in CMJ Stage 2 works.

Project information centre: 13-19 Howe St, Freeman’s Bay, Monday to Thursday
9.00am – 4.30pm, Friday 9.00am – 4.00pm, and Saturday by prior booking only.

Phone 0800 CMJ Core (0800 265 2673).

Transit New Zealand Regional Manager Richard Hancy tel. (09) 368 2000.
Visit www.transit.govt.nz for more information.

ENDS

© Scoop Media

Advertisement - scroll to continue reading
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 
 
 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

Featured News Channels


 
 
 
 

Join Our Free Newsletter

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.