CMJ traffic bulletin: Saturday 27 August until Thursday 1 September
Transit New Zealand would like to advise motorists of proposed closures for work on the Central Motorway Junction upgrade over the next week.
CMJ
Stage 2
Full motorway closures:
Sunday 28 until
Thursday 1 September - CLOSED - overnight from 9pm until
5.30am the following morning:
. Southern Motorway
(SH1) southbound between Cook St off-ramp and Hobson St
on-ramp
. Southern Motorway (SH1) northbound
between Nelson St off-ramp and Wellington St on-ramp
Ramp
and link closures:
Sunday 28 until Thursday 1 September -
CLOSED - overnight from 9pm until 5.30am the following
morning:
. Southern Motorway (SH1) to Nelson St
off-ramp citybound
. Southern Motorway to
Northwestern Motorway (SH1 to SH16 westbound) link
.
Gillies Ave on-ramp to Southern Motorway (SH1)
northbound
. Port to Northwestern Motorway and
Wellesley St on-ramp (SH16 westbound) link
.
Newton Rd on-ramp westbound to Northwestern Motorway
(SH16)
. Northwestern Motorway to the Southern
Motorway (SH16 to SH1 southbound) link
.
Northwestern Motorway (SH16) to Nelson St off-ramp
citybound
. Northwestern Motorway to Port (SH16)
port-bound link
. Northwestern Motorway (SH16) to
Newton Rd off-ramp citybound
. Western Springs
on-ramp eastbound to the Northwestern Motorway
(SH16)
Sunday 28 until Thursday 1 September - CLOSED -
overnight from 11pm until 5.30am the following morning:
.
Hobson St on-ramp westbound to the Northwestern Motorway
(SH16)
. Southern Motorway (SH1) northbound
between Symonds/Port/Wellesley off-ramp and Wellington St
on-ramp
Note 1: That on the nights that the Northwestern Motorway (SH16) to Newton Rd off-ramp is closed the Northwestern Motorway (SH16) to Nelson St off-ramp will remain open and vice versa.
Note 2: That on the nights that the Port to Northwestern Motorway (SH16) westbound link is closed the Newton Rd on-ramp to the Northwestern Motorway (SH16) will remain open and vice versa.
During these times motorists are requested to follow the signposted detours while the closures are in operation.
Transit New Zealand regrets any inconvenience caused.
In the event of inclement weather, the closures will be postponed to the next fine evening.
The CMJ
Project
Stage 1 of Transit's Central Motorway Junction
upgrade project, completed in January 2005, covers the
section of motorway between the Upper Queen St over-bridge
and Gillies Ave on- and off-ramps.
Phone 0800 ToFreeflow (0800 863 733).
Stage 2 of Transit's Central Motorway Junction upgrade project extends from Bond St on the Northwestern Motorway (SH16) to the interface with CMJ Stage 1 near Symonds St and from Cook St on the Southern Motorway (SH1) to Symonds St.
Project information centre: 13-19
Howe St, Freeman's Bay, Monday to Thursday
9.00am -
4.30pm, Friday 9.00am - 4.00pm, Saturday (except long
weekends) 10:00am - 12:00pm.
Phone 0800 CMJ Core (0800 265 2673).