Traffic growth key issue for Canterbury state highways
Traffic growth on the main arterial routes within Christchurch city makes congestion in Christchurch one of the key regional transport issues addressed by Transit New Zealand’s 10-Year State Highway Plan for the Canterbury region, released today.
Growth is running at 4 percent per year and up to 8 percent per year on the recently declared state highway on the Christchurch Ring Road, said Transit’s Canterbury regional manager, Robin Odams.
The plan outlines Transit’s forecast for spending on new road projects and maintenance in the region for the 2004/05 financial year and the nine years that follow. Large projects have been planned over 10 years and small and medium-sized projects over three years.
“Transit’s plan includes at least $231 million to construct new state highway projects in Canterbury in the next 10 years, $23.9 million of which will be spent in 2004/05. A further $24.8 million will be spent on maintenance in 2004/05, with a total of at least $360 million for maintenance in the next 10 years.”
“Some of the projects outlined in the plan may be built faster and others added with additional funding we anticipate from a share of the regional distribution funding resulting from the Government’s December 2003 funding package, ‘Investing in Growth’ raised through an increase in petrol tax,” Mr Odams said.
Investigations into access improvements in the north of Christchurch city, further development of the Christchurch southern motorway duplication and extension, and the four-laning of SH1 west of the city are major features of the plan.
“Ongoing improvements are required to the state highway network in Christchurch city and in Waimakariri and Selwyn districts to support urban growth.”
Mr Odams said these improvements would complement the Regional Land Transport Strategy provisions to relieve congestion through a range of measures including promoting passenger transport, completion of improvements to the “ring route” system, and improved access from the north and south of the city.
The SH74 Main North
Road Four-Laning (Stage 2) project is currently under
construction. The SH73 Christchurch Southern Motorway
Duplication and Extension project is planned for
construction within the next 10 years, Mr Odams
said.
Other improvements either under construction or
recently completed include:
• Normanby Realignment on SH1
south of Timaru
• Omihi Passing Lanes on SH1 north of
Amberley
• Hurunui Curves on SH7
• Omihi Twin Culverts
Realignment and Passing Lane on SH1.
“Transit’s long-term plan is to four-lane Johns/Russley/Masham/Carmen Roads. This could happen within the next 10 years, depending on funding,” he said.
In the meantime, a number of
intersection improvements on this route are being
undertaken. These include:
• SH1 – Yaldhurst Road
Intersection Signalisation
• SH1 – Buchanans Road
Intersection Signalisation
• SH1 – Main South Road/Carmen
Road Intersection Improvements at Hornby.
Mr Odams said Transit had retained the Northern Arterial, north of Queen Elizabeth II Drive, as a potential project.
“The timing of the Northern Arterial is likely to be dependent on the development of an effective local road network, south of QEII Drive, to feed the Northern Arterial. Likewise, the Western Belfast Bypass and four-laning of a section of Queen Elizabeth II Drive are included as potential projects for further investigation.”
Within Waimakariri District, there are long-term plans to complete the duplication of the Northern Motorway and construct a bypass of Woodend on SH1, and to four-lane SH71 to Rangiora. At this stage, no route has been determined for a bypass of Woodend, he said.
Within Selwyn district, the major long-term requirement identified by Transit is to four-lane SH1 between Christchurch and Rolleston, with an appropriate connection into Rolleston to serve the urban growth proposed for this area. This may also include the eventual further extension of the Southern Motorway to Main South Road.
Road safety is also highlighted as an important
issue in the Canterbury region. A number of small and
medium-sized safety proposals for construction over the next
three years include rural realignments, guardrails and
intersection improvements.
Another key safety improvement
will be the further implementation of a strategy for the
provision of stock effluent disposal facilities that has
been agreed with local authorities in the region. Disposal
facilities are almost complete at Tinwald and Glasnevin on
SH1 and additional facilities at Kaikoura, Springfield and
Pareora are included in the plan.
Passing lanes have been completed over the last year on SH1 at Waipapa and Winslow. Additional passing lanes are included in the 10-year plan to complete Transit’s current passing lane strategy for SH1 between Kekerengu and Timaru.
Consultation played an important role in the development of the plan within the context of the new Land Transport Management Act (passed in November 2003), said Mr Odams. All large project proposals have been reviewed to ensure integrated solutions that fitted with Canterbury’s local authority plans and that the benefits of the plans were sustainable, Mr Odams said.
Major features included in the Canterbury 10-year
plan are:
• investigations into access improvements to the
north of Christchurch city – the Northern Arterial and
Western Belfast Bypass and the four-laning of a section of
QEII drive
• safety improvements for construction in the
next three years include:
o East/West Street Intersection
in Ashburton
o South Street/SH1 Intersection in
Ashburton
o Kerrytown Road Curve Realignment
• further
development and construction of the Christchurch Southern
Motorway duplication and extension and development of the
four-laning of SH1 (Carmen/Russley Roads) west of the
city
• three more stock effluent disposal sites at
Pareora SH1, Kaikoura SH1 and Springfield SH73
• cycle
facilities within Christchurch city and on the Jed, School
and Boyle River bridges
• Construction of passing lanes
at another 12 locations on SH1.