INDEPENDENT NEWS

Cablegate: February 17 Aborted Wealth-Sharing Working Group Planning

Published: Thu 21 Feb 2008 04:20 PM
VZCZCXYZ0003
PP RUEHWEB
DE RUEHKH #0258/01 0521620
ZNR UUUUU ZZH
P 211620Z FEB 08
FM AMEMBASSY KHARTOUM
TO SECSTATE WASHDC PRIORITY 0009
UNCLAS KHARTOUM 000258
SIPDIS
DEPT FOR AF/SPG, S/E WILLIAMSON
DEPT PLS PASS USAID FOR AFR
SIPDIS
SENSITIVE
E.O. 12958: N/A
TAGS: PREL PGOV PINS ECON EAID SU
SUBJECT: FEBRUARY 17 ABORTED WEALTH-SHARING WORKING GROUP PLANNING
SESSION AND THE NEED TO STRENGTHEN SPLM CAPACITY AT AEC WORKING
GROUP MEETINGS
1. (U) SUMMARY: In the February 17 meeting of the Wealth Sharing
Working Group (WSWG), the SPLM representative admitted he was
neither prepared, nor qualified to speak on behalf of his party.
The NCP accused the AEC secretariat of failing to deliver a document
outlining the structure of the mid-term evaluation. The NCP
representatives also assumed that their suggestions were accepted in
the February 5 plenary, although these ideas were not formally
agreed to by both parties. Suggestions for strengthening the AEC
are outlined in para. 12. END SUMMARY.
NCP AGGRESSIVE AND SPLM UNPREPARED
----------------------------------
2. (U) The U.S. coordinator of the Wealth Sharing Working Group
opened the February 17 session asking for the parties' priorities
and work in the coming months. The NCP's Muhammad Mukhtar Al Hassan
noted that the Working Group faces the dual challenges of completing
the mid-term evaluation while carrying on its normal work. He
stated that the matrix should be the basis for the mid-term
evaluation.
3. (U) Al Hassan continued that the AEC secretariat was to have
submitted a proposal outlining the structure of the mid-term
evaluation within two days of the AEC plenary, but had failed to do
so. "We need this document to unify the method and structure of the
mid-term evaluation," he said. (NOTE: Plenary minutes do not
mention a deadline associated with the drafting of this document:
"The Chairman agreed with the NCP and said that the Secretariat
would begin work on a structure of the mid term review immediately."
END NOTE.)
4. (U) The Norwegian representative replied that the Terms of
Reference (TOR) for the mid-term evaluation have only been "accepted
in principle" and will be completed at the next AEC plenary. He
stated that while Norway has received feedback from the NCP on the
TOR, it is awaiting SPLM input. He said that the secretariat is
working on a draft document outlining the structure of the mid-term
evaluation.
5. (U) The WSWG coordinator then requested input from SPLM
representative Khalid Ja'dain. Ja'dain responded that he was a last
minute fill-in for the SPLM, and was neither prepared nor qualified
to speak on behalf of his party. As the SPLM representative could
make no decisions, the NCP representatives suggested adjourning the
meeting. The SPLM agreed, and the coordinator accepted their
decision noting, "We need more than just attendance, we need people
who are prepared and knowledgeable about these issues."
6. (U) Before the meeting adjourned, the NCP noted the fast
approaching April 15 deadline for the first draft of the Mid-Term
Evaluation (MTE). They suggested that the Working Groups meet
weekly to accelerate the drafting process. They added that the last
plenary session agreed that the AEC will designate a primary
drafter, who would not be involved in the analytical work.
Additionally, the NCP interpreted the plenary discussion as
concluding that experts for the MTE will be hired only for
particular issues when a second opinion is needed.
7. (U) The WSWG coordinator said that the MTE should do more than
just evaluate whether CPA-mandated mechanisms have been established,
but should evaluate the performance of those institutions as well.
Before the meeting was adjourned the NCP stated again that they
expect the AEC to draft a document outlining the structure of the
MTE, "or we will just do it ourselves."
8. (SBU) After the meeting, Norwegian representative Nicolas
Stivang told econoff that Muhammad Muktar Al-Hassan decided from the
start of the meeting that he was "going to go on the offensive and
attack the non-existent AEC secretariat." Stivang continued that
the NCP representatives appear to have many assumptions about what
was actually decided at the last plenary session, not all of which
are entirely accurate. Stivang stated, "The AEC is supposed to be a
venue for cooperation between the parties in both letter and spirit.
Right now, the NCP is only honoring it in letter."
9. (SBU) EconOff also spoke with Abdelmoneim Mustafa Elamin, the
AEC Executive Secretary, after the meeting. He stated that he was
unaware that the AEC was to draft a document outlining the structure
of the MTE. Elamin also inquired when the new AEC coordinator, Sir
Derrick Plumley, would arrive in Khartoum.
10. (U) Participants:
U.S. Embassy: Roberto Powers, Deputy Chief of Mission,
Eric Barbee, Economic Officer
NCP: Hassan Ahmed Omar, Mohamed El-Mukhtar Al-Hassan
SPLM: Khalid Jadain
Norwegian Embassy: Nicholas Strivang, Political Affairs Officer
UNMIS: Khalid Elsawi, Political Affairs Officer
UNDP: Auke Lootsma; Deputy Country Director
French Embassy (for EU Presidency): Vicent Schneiter, Economic
Counselor
AEC COORDINATORS REVIEW OPTIONS
-------------------------------
11. (SBU) On February 21, AEC coordinators met to review the
situation and discuss ways of accelerating the Mid-Term Evaluaion
process. Acting AEC Chair, Norwegian Ambassador Thorkildsen,
reported that Ambassador Plumley plans to arrive on March 16. He
said that the NCP has accepted the TOR and the SPLM expects to do so
in the next few days. The Dutch Ambassador reported progress in the
Three Areas Working Group. DCM Powers reported on the aborted
February 17 WSWG meeting and noted lack of SPLM capacity and NCP
delaying tactics as key impediments. The UK Ambassador said that
the Security Working Group faces challenges similar to those with
the WSWG and is moving forward only slowly. The Italian Ambassador
said that work in the Power Sharing Working Group has been
constrained by lack of embassy staff, but hopes that situation will
soon improve.
12. (SBU) The coordinators agreed that strengthening SPLM capacity
is a key requirement to keeping the MTE and other AEC activities on
track. Ambassador Thorkildsen said he has been discussing ways to
do so with Kosti Manibe of the SPLM and added that Norway may be
able to fund a full-time Secretariat position to serve as MTE
drafter. DCM noted that the NCP has made clear they do not favor an
outside drafter and expect the Working Group Coordinators to draft.
COMMENT
-------
13. (SBU) In the coming months the AEC will face a number of
difficult challenges. The first is how to make the mid-term
evaluation both useful and unity-enhancing for the parties. Some
among the parties would like nothing better than to politicize this
process and fixate the AEC on the minutiae of drafting. While the
appointment of the new chairman is welcome, we should not assume
that his arrival will instantly transform the AEC into a fully
functional body. Other steps need immediate attention to support
this fragile CPA institution. End Comment.
PROPOSALS TO STRENGTHEN THE AEC
-------------------------------
14. (SBU) Working Group coordinators and AEC secretariat should
consider taking the following steps to empower the AEC at this
critical juncture:
WORKING GROUPS
--------------
- Establish weekly or bi-weekly working-level meetings for
political officers assigned to work on the AEC from the UK, U.S.,
Italy, and the Netherlands. Focus on improved coordination among
AEC coordinators, especially at the working level.
- Continue pre-meetings for AEC plenary sessions for Khartoum
Ambassadors.
- Keep an accurate accounting of all efforts and actions taken by
Working Group coordinators to organize working group meetings.
Submit actions to AEC secretariat on a monthly basis.
- Set tone and spirit of cooperation at all working group meetings.
- AEC SECRETARIAT
-----------------
- Make use of AEC rules and procedures for formally accepting any
decision at plenary sessions.
- Establish timeline for the arrival of the German legal expert, an
additional administrator, and the new chairman. Communicate
expected schedule to parties, AEC administrative staff, and working
groups.
- Bolster leadership of Chairman at every opportunity.
- Promptly draft detailed minutes of plenary sessions, clearly
identifying any mutually agreed decisions made at each session.
- Send one representative from AEC secretariat to all working group
meetings for improved continuity and coordination.
- Enhance transparency of AEC with a more expanded public website.
- Develop better contact lists of coordinators, SPLM and NCP
representatives, and their backups.
- Set tone and spirit of cooperation at all plenary sessions.
- SPLM AND NCP:
--------------
- Expand the number of representatives (especially the SPLM)
available for the AEC. (Current SPLM representatives are overworked
and struggling with multiple demands on their time and energy.)
- Designate one point of contact for confirming attendance at
scheduled meetings.
- Take more initiative to propose meetings, as opposed to reacting
to the ideas of the working group coordinators.
- Provide regular updates from political executive committee.
- Express intention to commitment of AEC and to working together
in the spirit of the CPA.
FERNANDEZ