Foundation pour cements signs of progress

Published: Wed 27 Feb 2013 12:02 PM
Hon Gerry Brownlee
Minister for Canterbury Earthquake Recovery
27 February 2013 Media Statement
Foundation pour cements signs of progress
Canterbury Earthquake Recovery Minister Gerry Brownlee says a foundation laying project that will get underway in the heart of central Christchurch early tomorrow is another positive step in the city’s rebuild.
“For 13 straight hours almost 750 cubic metres of concrete will be laid on the site of a new office building on the corner of High and Lichfield Streets, starting at 3am on Thursday,” Mr Brownlee says.
“This concrete pour is the largest within the rebuild zone so far and the four story office building going on the site will be completed by December.”
The building is being built by Leighs Construction, who will be a tenant in the new offices.
“This is a great example of a proactive property owner getting their feet firmly under the table and securing a place in the new city centre,” Mr Brownlee says.
“It is one of many construction sites behind the rebuild zone cordon at present, but as that cordon is reduced in the coming months the public will see just how much progress is being made.”
The rebuild zone cordon is on target to be completely removed by the end of June when Defence personnel manning the cordons will withdraw. There will be several progressive cordon reductions between now and then.

Next in New Zealand politics

Maori Authority Warns Government On Fast Track Legislation
By: National Maori Authority
Comprehensive Partnership The Goal For NZ And The Philippines
By: New Zealand Government
Canterbury Spotted Skink In Serious Trouble
By: Department of Conservation
Oranga Tamariki Cuts Commit Tamariki To State Abuse
By: Te Pati Maori
Inflation Data Shows Need For A Plan On Climate And Population
By: New Zealand Council of Trade Unions
Annual Inflation At 4.0 Percent
By: Statistics New Zealand
View as: DESKTOP | MOBILE © Scoop Media