31 March 2006
New project leaders keen to progress Greater Christchurch UDS
Getting four councils and Transit New Zealand to agree and draft an Urban Development Strategy to deal with future
growth in Greater Christchurch is not impossible or difficult, say the consultants leading the project.
Ken Tremaine and Bill Wasley have been taken on as joint project leaders to lead and help implement the UDS - Mr
Tremaine, from Auckland, as technical specialist and Mr Wasley, from Tauranga, the governance specialist.
Between them they have managed the successful Bay of Plenty Smartgrowth project that Prime Minister Helen Clark launched
on 14 May 2004. Smartgrowth was set up to ensure that, as Western Bay of Plenty grows, it continues to be a great place
to live, work and play.
The two helped Tauranga City, the Western Bay of Plenty District Council, and Bay of Plenty Regional Council draft and
implement a Western Bay of Plenty strategic growth management plan. The Government was impressed enough to match
dollar-for-dollar Western Bay of Plenty’s clean transport plan for 10 years, netting a total $300 million for the
sub-region’s transport.
“My big interest is in big-scale development planning in New Zealand and internationally, to look long-term at landuse
and the social implications of that in housing, health, transport, and a fair means of funding this. In the past, New
Zealand has not been too good at knowing the cost of growth or delivering timely zoning and infrastructure at a fair
price to support it,” Mr Tremaine says.
Long-term strategising is a major learning curve for Canterbury authorities - who must ignore historical boundaries to
plan and seek solutions together - and central Government, which gets nervous when individual local governments seek
funds for infrastructure. “It’s about connecting the head, heart, and funding. You collate the great ideas, build
community passion for it, then seek the means to deliver it,” Mr Tremaine says.
“Smartgrowth attracted Central Government funding because it provided a growth management strategy that all agreed to,
then identified key infrastructural needs and practical solutions that could be achieved with adequate funding,” he
says.
Mr Wasley says his challenge is to keep all the Greater Christchurch partners fully engaged in the process. “That won’t
always be easy, but it is achievable and realistic. It will take time because it’s about understanding each others’
issues and positions, but developing trust to consider what’s best for the metropolitan sub-region as a whole.”
“It is about nurturing a culture of partnership and collaboration on a long-term basis. Working together sends all the
right signals to Government that Greater Christchurch partners can deliver together long-term. It’s about having a
metropolitan sub-regional vision, which is both urban and rural, but shares similar goals of safe, vibrant communities
with a sense of place, a means of getting around easily, clean water and air, and a variety of sustainable, affordable
housing,” Mr Wasley says.
Completion Timeline for Greater Christchurch UDS
Stage One
Strategy drafting Mid March to late April 2006
Charette process
Urban development design and planning process (charette) Late April to end of May 2006
Elected members and Urban Development Strategy Forum input (between conclusion of charette and draft strategy) End of
may to end of June 2006
First draft of Urban Development Strategy End of June 2006
Activity Manager sign-off
Confirmation of draft Urban Development Strategy by key activity and asset managers from all Greater Christchurch UDS
partners Mid July 2006
Elected Member and UDS Forum Engagement
(pre-Strategy notification review) August 2006
Notification of the draft Greater Christchurch Urban Development Strategy after UDS partners agree to release it for
public consultation End of August to mid September 2006
Review project time line End of August
Stage Two
PUBLIC CONSULTATION Mid September to mid October, 2006
Submissions close
Analysis, hearings, strategy modification Mid November to mid December, 2006
Elected members and UDS Forum engagement December to mid February 2007
Implementation
Ongoing work on Strategy actions, formal implementation structure agreed to, monitoring framework put into place
February to April 2007
Implementation tools
- LTCCP amendment
- Regional Planning Strategy scope
- Regional Land Transport Strategy alignment May to June 2007